Issue - decisions

ICT Programme Approvals

03/12/2009 - ICT Programme Approvals

Resolved:

 

i)                    That the Committee approve a waiver of the Council’s Contract Procedure Rules such that procurement of the Northgate Revenues and Benefits IT system be undertaken using the Office of Government Commerce Catalist Framework Contract.

ii)                  That the Committee approves delegated authority to the Corporate Director (s151) in consultation with the Chairman of Policy and Resources Committee to appoint suppliers or contractors.

 

 

Reason:

 

To ensure that the Revenue and Benefits service does not suffer the adverse effect of any future termination of the Civica product, and in order to achieve revenue efficiency savings.

 

 

 

 

 

 

PART ‘B’ – MATTERS REFERRED TO COUNCIL